The Permanent Conference of Services for road construction sites and eventsin which all the Municipalities, Services and bodies involved are regularly invited to participate and which meets on a weekly basis, approved in the presence of representatives of the Local Police Service, the Roads, Roads and Traffic Service, the Event Management Service and DA Maradona Stadium, the Culture Service, the Department of Sport and Equal Opportunities, Municipality 4, the 2i ReteGas Spa Company and e-Distribuzione Spa, some construction sites that will affect the following roads:

Dal 15/04/2024for a duration of 60 days, cleaning activities were started along theroad axis of the Scampia Perimetral. The operations will be carried out with open traffic, starting from Capodichino in the direction of Melito and continuing in the opposite direction, without closing the ramps, with a mobile construction site appropriately signposted and guaranteeing the passage of vehicles at every stage.

Dal 22 al 04/30/2024 as part of the energy efficiency works of the public lighting system powered by the M054 “Vomero” cabin, the replacement operations of the supports and lighting bodies will be carried out by the company Elettrovit Srl, in via Gino Doria, via Belvedere e via San Gennaro al Vomero. Given the configuration of these roads and the type of work to be carried out, it is necessary to close them to vehicular traffic according to the following phases and methods:
Phase 1 – 04/22/2024 – via Gino Doria, stretch between the civ. 79 and the intersection with via Antonio Pitloo: – the parking stalls in the stretch between via Antonio Pitloo and via Francesco Solimena will also be suspended and the paid parking stalls in via Antonio Pitloo will be suspended.
During the closure of the affected section to transit, vehicles heading to via Pitloo will be able to turn into via Consalvo Carelli, and proceed along via Francesco De Mura, via Giovanni Merliani and via Massimo Stanzione;
Phase 2 – from 23 to 24/04/2024 – via Gino Doria, stretch between Francesco Solimena and the confluence with via Alessandro Scarlatti: – parking stalls will be suspended.
During the closure of the affected section to transit, vehicles heading towards Via Cilea will be able to turn onto Via Francesco Fracanzano, while vehicles heading towards San Martino will be able to turn onto Via Francesco Solimena;
Phase 3 – 04/26/2024 – via Belvedere, stretch between the civ. n. 95 and Calata San Francesco – as well as for the stretch indicated above, a ban on vehicular transit will be established, except for residents and those heading to authorized driveways, also in via Belvedere, from the confluence with via Santa Maria della Libera up to number no. . 95 (bottleneck height), with two-way traffic;
– it is also planned to reverse the direction of travel in Calata San Francesco, to allow vehicles to proceed along the stretch of via Belvedere, regulated as one-way, between the confluence with Calata San Francesco and the confluence with via G Doria.
Alternatively, vehicles coming from Via Belvedere on the mountain side and heading towards Via Cilea can turn onto Via Santa Maria della Libera. Residents in via Calata San Francesco or in via Belvedere beyond the civ. 95, entrance from via Aniello Falcone in the direction of via Belvedere and viale II Malatesta.
Phase 4 – 04/29/2024 – via Belvedere, stretch between Calata San Francesco and Vico Belvedere. Alternatively, vehicles coming from via Belvedere on the mountain side and heading towards via Aniello Falcone can, alternatively, turn onto via Santa Maria della Libera, via Cilea, via Gino Doria or continue on via Belvedere and turn onto Calata S. Francesco.
Vehicles coming from Vico Belvedere continue along Via Belvedere towards Via Gino Doria and, finally, vehicles heading towards Viale II Malatesta will be able to travel along Vico Belvedere and Via Belvedere.
Phase 5 – 04/30/2024 – via San Gennaro al Vomero, stretch between the intersection with via Gian Lorenzo Bernini and via Enrico Alvino: – the parking stalls on both sides will be suspended.
Vehicles heading to via San Gennaro in Antignano will be able to proceed along via Gian Lorenzo Bernini and then enter via Vincenzo D’Annibale.
All work will take place during daytime from 8:00 to 16:00. During the closures, access will be guaranteed to residents (and authorized driveways), emergency vehicles and law enforcement vehicles.
At the end of each phase, the interesting road sections will be regularly reopened to vehicular traffic.

See also  A tangible shift towards sustainability in the energy sector

Dal 04/22/2024 al 05/10/2024 the redevelopment works of the central traffic island will be carried out viale Augusto, in the stretch between via Attilio Regolo and via Sebastiano Veniero. During the works which will be carried out in open traffic, a parking ban will be established along the roadway towards Piazza Italia. In the roadway in the direction of Piazzale Tecchio, a 3 m strip will be created to allow the approach of construction site work vehicles, therefore the works will be carried out in open traffic with narrowing of the roadway and a ban on parking in the affected section. In order to to ensure pedestrian traffic, temporary pedestrian crossings will be created, where necessary, at the beginning and end of the construction site.

Dal 04/22/2024 al 07/05/2024the works for the creation of the joint holes and subsequent insertion of cables for the strengthening of the MV electricity lines will be carried out by e-Distribuzione Spa, in via Aquileia, via Cimitero Israelita, via Vicinale Cannola, via Cannola, corso Malta, via Lahalle and via Arenaccia according to the following phases and methods:
Phase 1 – from 04/22/2024 to 05/10/2024 – via Aquileia, in the stretch between the ENEL cabin and the intersection with via Cimitero Israelita, advancing 5.00 m beyond the public lighting pole no. 229053, with traffic closed. During the closure to vehicular traffic, to access the upper part of Via Aquileia, it is expected to travel from Via Nuova Poggioreale onto Via Vicinale S. Maria del Pianto, without altering the regular circulation of traffic, in the same way for the lower part of Via Aquileia, at the intersection with Via Cimitero Israelita, where the journey will take place on the latter;
– Phase 2 – from 13 to 14/05/2024 via Cimitero Israelita in the stretch between via Aquileia and the ABC headquarters, the works will be carried out with closed traffic. To allow access and exit of vehicles from the ABC headquarters, an alternate one-way system will be established up to via Nuova Poggioreale;
– Phase 3 – from 13 to 22/05/2024 via Vicinale Cannola will continue with open traffic;
– Phase 4 – from 23 to 31/05/2024 we will continue, with open traffic, with the creation of a second hole in via Vicinale Cannola and subsequently on via Cannola;
– Phase 5 – from 03 to 14/06/2024 Corso Malta service road, on the military district side, in the stretch between the intersection with Via Piazzolla and the intersection with Via Lahalle. The closure of the service road is expected and access to the EI barracks will be possible from other existing vehicle accesses on its perimeter roads;
– Phase 6 – from 10 to 28/06/2024 via Lahalle we will continue with the opening of the joint hole and the insertion of cables in the center of the road, where the excavation works for the laying of pipes have already been carried out, with a mobile construction site, with open traffic and with the establishment of a ban on parking on both sides along the stretch affected by the works from time to time;
– Phase 7 from 01 to 05/07/2024 via Arenaccia starting from the confluence with via Lahalle towards piazza Ottocalli, in this phase the construction site will have a footprint of approximately 20 m. and the works will be carried out with open traffic.

See also  Inter wins 2-0 in Venice and puts pressure on Milan and Naples

Regarding the events:

Il 03/05/2024in the context of “May of Monuments 2024”, the “Volta Celeste” event will take place in Piazza Municipio, an acrobatic show featuring artists on stilts and an aerial performance by an artist who will be suspended and hooked to a crane, approximately 10 meters above the ground. The show will begin after sunset and end no later than 10.30 pm. For the setting up of the crane, which will begin from the morning of the date on which the event will be held and which will be positioned in the stretch of Piazza Municipio between number 4 and via Ruggero Leoncavallo, it is necessary to prepare a particular traffic device which involves:- the reversal of the direction of travel of via Ruggero Leoncavallo, so as to allow cars coming from Piazza Municipio to turn right;
– the closure to traffic of the road section between the intersection between Piazza Municipio and Via Ruggero Leoncavallo and number 4;
– the establishment of two-way traffic in the stretch between Piazza Municipio Civ. 3 and the intersection between Piazza Municipio and via Vittorio Emanuele III, necessary to allow the entry and exit of the condominiums of the civ. 4.

You may also like

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More

Privacy & Cookies Policy