53 projects in the two major competition areas of the Beijing Winter Olympics were completed, the opening and closing ceremony venue “Bird’s Nest” renovation completed in October|Beijing Winter Olympics|Yanqing|Beijing_Sina News

by admin

Source: Beijing Daily

Original title: 53 projects completed in the two major competition areas of the Beijing Winter Olympics, the opening and closing ceremony venue “Bird’s Nest” renovation completed in October

On July 19, there will be a 200-day countdown to the opening ceremony of the Beijing 2022 Winter Olympics. How is the progress of the Winter Olympics project? According to the Beijing Major Projects Office, as of July 17, Beijing and the Yanqing Winter Olympics were responsible for the construction of 57 Winter Olympics projects, and 53 projects have been completed. The remaining 4 projects are scheduled to be completed in 2021. The renovation of the National Stadium “Bird’s Nest”, which is responsible for the opening and closing ceremonies, will be fully launched on July 4 and is scheduled to be completed in October 2021.

Going all out to prepare for the Beijing Winter Olympics and Paralympics is one of the two major events in Beijing in 2021. According to the relevant person in charge of the Municipal Major Project Office, the 8 competition venues in Beijing and Yanqing have been fully completed by the end of 2020. The “two pavilions and one village” in the Yanqing competition area for the Winter Olympics were completed in mid-July, and the ecological restoration work was completed by the end of June. The design concept of “Mountain and Forest Venues, Ecological Winter Olympics” changed from a blueprint to reality, realizing the integration of the development of sports undertakings with the promotion of ecological civilization construction, making the first-class Winter Olympics facilities and the natural landscape of Xiaohai Tuo harmoniously blended.

See also  Full-process online litigation enhances the public’s sense of justice. Online trial rate is 67.4%, ranking first in the country | Court | Beijing_Sina News

At the same time, the eight competition venues completed in the two competition areas, transportation, water, electricity, communications and other supporting facilities meet the requirements of venue commissioning and test activities. The eight competition venues have passed all-round testing and inspection of competition activities.

Among the 9 non-competitive venues in Beijing and Yanqing competition areas, 7 have been completed. Among them, the Beijing Winter Olympic Village and the main media center of the National Convention Center Phase II were delivered in June 2021. The first comprehensive project of the Winter Sports Center was completed and accepted in June. As the final work of the construction and renovation of the Beijing Winter Olympics and Paralympic Winter Games venues, the construction and renovation of the opening and closing ceremonies of the National Stadium “Bird’s Nest” has been fully launched on July 4 and is scheduled to be completed in October 2021.

The preparations for the Winter Olympics have entered a critical period of full sprint, comprehensive preparation, and decisive victory. Beijing Winter Olympics construction will continue to adhere to the first-level standards, promote the spirit of craftsmanship, strive for excellence, and further improve the venue and facilities in accordance with the standards to ensure that the venues and competition areas as a whole meet the requirements. Competition standards, promote the full closure of venues and supporting infrastructure, and fully implement the requirements of “simple, safe and exciting” for running the competition. (Ren Shan)

.

You may also like

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More

Privacy & Cookies Policy