Afinia reported this Saturday, January 13, that next week it will carry out work to strengthen its technical management and provide better service to the inhabitants of the Cesar departments, so will suspend the energy supply in several municipalities of these territories where the work will be carried out.

The service will be suspended in the following municipalities:

MONDAY, JANUARY 15

-Rural area of ​​Valledupar: from the 6:45 a.m. until 5:45 p.m.new structures will be installed, armed with medium voltage on the line that supplies energy to customers located in the townships Aguas Blancas and Mariangola.

-The Jagua of Ibirico: The operating team will remove the mechanical protections, which is why the energy service will be suspended to the users that supply energy to the Circuit. The Jagua 3from the 9:00 a.m. until 5:45 p.m. in the neighborhoods Galán, 17 de Febrero, Galancito, El Bosque, La Florida, Bello Horizonte; Boquerón district, Juan Ramón, Communeros, Progreso, November 20, Nuevo Milenio, Villa Nancy Urbanization, Altos de La Mina Urbanization, Sororia Urbanization.

-Astrea 1 circuit: of 10:45 a.m. a 3:30 p.m., For safety reasons, it is necessary to suspend the electricity on Carrera 7 and Calle 21 in the 11 de Noviembre neighborhood in Astrea, to renew elements in the network.

TUESDAY, JANUARY 16

-La Jagua 2 Circuit: To carry out a technical day, the energy service will be interrupted in several places in La Jagua de Ibirico: from 10:45 am to 1:45 pm, in Kilometer 1 sectors surrounding the highway to La Palmita. From 2:30 pm, on Calle 2A with Carrera 2. From 1:50 pm to 5:45 pm, on the La Conquista sidewalk.

See also  Always squeezes...

-San Roque Circuit: the technical team from 10:45 a.m. until 1:45 p.m.., will make adjustments to the circuit with the driving of poles and medium voltage reinforcement. To carry out this activity, the electricity supply will be suspended to the inhabitants of the Santa Isabel district and sectors surrounding the road to San Roque – Santa Isabel.

WEDNESDAY, JANUARY 17

-Guatapurí Circuit 4: The installation of semi-direct measurement equipment will be carried out, an activity that requires the suspension of the electrical fluid between the 10:00 am and 2:00 pmon Carrera 38 with Calle 5 D Francisco El Hombre sector in Valledupar.

-La Jagua Circuit 1: The installation of semi-direct measurement equipment will be carried out, an activity that requires the suspension of the energy service from the 12:35 pm until 5:00 pm. to users located on the highway via Sierra Kilómetro 8 Sectors surrounding Finca Mi Futuro.

-Patility Circuit 1: from the 7:45 pm until 5:15 pmnew structures will be installed, armed and preventive activities will be carried out in the circuit that supplies energy to customers located in the Carmen, El Bosque, Los Fundadores, La Frontera neighborhoods in the urban area of ​​the municipality of Bankruptcy.

THURSDAY, JANUARY 18

-Circuito Bankruptcy ll: The energy company operators continue the installation of new poles and medium voltage installations, therefore, they will be without electricity between the 7:40 a.m. until 5:40 p.m.., users on the sidewalks La Esperanza, Zapatín and El Progreso in Chimichagua.

-La Jagua 2 Circuit: The installation of semi-direct measurement equipment will be carried out, an activity that requires the interruption of service between 2:15 pm and 6:00 pm, to users located at kilometer 8 sectors surrounding the road The saw.

-Line 5162: of 10:50 a.m. a 3:00 p.m., semi-direct measurement equipment will be installed, a task that requires suspending the energy in Chiriguana in the La Aurora district and in kilometer 6 sectors surrounding the El Cruce de La Sierra road.

See also  EPM manager to President Petro

FRIDAY, JANUARY 19

-Circuit Tamalameque: With full commitment, the work of installing new structures, assembling medium voltage and removing branches that interfere with the electrical networks will continue, for which it is necessary to interrupt the electricity service. 7:55 am to 5:30 pm, in the following sectors in the municipality of Tamalameque: El Jobo, 12 de Octubre and Puerto Boca.

-Codazzi Circuit 3: Optimization will be carried out in the electrical infrastructure, activities that require the suspension of electrical fluid on 12th Street with Carrera 1B sector in the La Frontera neighborhood in Agustín Codazzi.

SATURDAY, JANUARY 20

-Becerril 2 Circuit: The installation of semi-direct measurement equipment will be carried out, an activity that requires the suspension of the electrical fluid between the 1:00 pm and 6:00 pm, on Carrera 7 with Calle 10, sector of the neighborhood Center in Becerril.

You may also like

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More

Privacy & Cookies Policy