ITA BiH planned modernization. 500,000 KM each planned for the reconstruction of GP Uvac and Strmica,

Izvor: Shutterstock

It was confirmed for Avaz from the Administration for Indirect Taxation (ITA) of BiH.

That process is still ongoing, as it was said, the Administration is in the phase of obtaining urban approval from the Federal Ministry of Spatial Planning.

Contractor

“After obtaining urban planning approval, we will continue with further activities on obtaining a building permit and announcing a public procedure in connection with the selection of a contractor for the construction of the new Doljani border crossing. At the moment, the ITA has 3.2 million KM at its disposal, according to the decision on multi-year capital investments of the Administration “, said Ratko Kovačević, spokesperson of the ITA BiH.

Let us remind you that the story about the construction of the new GP Doljani, one of the most frequented in the south of our country, started back in 2017. A year later, land was purchased in the amount of almost one million KM, in the immediate vicinity of the existing crossing, which covers 4,300 square meters.

However, this border crossing is not the only one that the ITA intends to build. Unlike GP Doljani, the process of realizing the construction and equipping of GP Osoje, in the area of ​​Posušje, is ongoing, for which 5,850,000 KM has been approved in the ITA budget. When it comes to the construction of GP Čepikuća, the project documentation is being prepared, and the total value of the project is one million KM.

After 500,000 KM

See also  Debt Case to Aline Adita, Codeblu Insists on Money Lost to Investment Risk

“ITA BiH plans to continue investing in the construction of new and reconstruction of existing border crossings this year. When it comes to the construction of new border crossings, in 2024 it is planned to build a new international GP Uvac – Uvac between BiH and the Republic of Serbia, whose value is estimated at 500,000 KM, as well as the new GP between Bosnia and Herzegovina and the Republic of Croatia Strmica – Strmica, whose value is also estimated at 500,000 KM,” Kovačević said.

When it comes to the reconstruction of the existing border crossings, the international border crossing Izačić – Ličko Petrovo Selo is planned for 2024, for which 500,000 KM is necessary, as much as for the Rača – Sremska Rača crossing. 400,000 KM is planned for the reconstruction of the crossing Ustibar – Ustibar and 300,000 KM for the crossing Ripač – Užljebić.

Zupci i Brod

When it comes to the reconstruction of GP Zupca, a contract was signed with the contractor. Funds in the amount of 5.5 million KM were approved for the construction of GP Zupci and Klobuk. In connection with the reconstruction of GP Brod, property relations are being settled, and the total value of the project is one million KM. Also, the settlement of property relations for the construction of a facility to house the customs service and the Border Police of BiH at Banja Luka Airport is underway. The total value of this project is 3,650,000 KM.

(World)

You may also like

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More

Privacy & Cookies Policy