Valledupar and municipalities of Cesar that will be without power between March 4 and 6

Afinia, a subsidiary of Grupo EPM, announced that it will carry out activities from March 4 to 6 in several circuits to strengthen the Cesar energy service.

However, to protect the integrity of its operators, the service will be interrupted while they carry out optimization work in the following municipalities:

Monday March 4

-Rural area of ​​Agustín Codazzi: From 7:10 am to 5:45 pm, new structures will be installed, armed with medium voltage and technical pruning will be carried out on the Casacará circuit, which is why the energy service will be suspended on Carrera 7 with Calle 12 in the Casacará district.

-Chimichagua: technical brigades will renew a distribution transformer from 6:30 am to 12:00 pm, work that requires the suspension of the electricity supply in the sectors surrounding the road to Chimchakuy in the Mandinguilla correction; and from 1:00 pm to 6:00 pm, in sectors surrounding the road to Las Mulas.

Tuesday March 5

-Casacara Circuit: The technical team will install poles, armed with medium voltage and will carry out technical pruning, for which, From 7:10 am to 5:45 pm, the electricity supply will be suspended in Carrera 3 with Calle 9 and 10 in the Casacará district. in Agustín Codazzi.

Chimichagua: renovation works will be carried out a distribution transformer from 6:00 am to 4:00 pmtime that the electricity supply will be suspended in sectors surrounding the Villanueva Estate.

Wednesday March 6

Valledupar: engineers and technicians will carry out the change of protections, downpipes and lightning rods of a transformer equipment, an activity for which the energy service in the Mariangola 1 circuit will be suspended. from 9:40 am to 5:00 pm, in the sectors surrounding Finca Lusitania via the Los Venados district.

See also  Filed application for Urban License of the Alameda Martha Mojica Partial Plan in Yopal – news

-Agustín Codazzi: specialized personnel will carry out maintenance the La Europa substation from 8:00 am to 5:00 pmtime that the La Europa and Puntarrecha paths will be without power: sectors surrounding the San Carlos farms, La Lopera, La Danta, La Montaña, El Humar Villa Daniela, Villa Rita, Villa Ruth, Villa Nadian, Santa Rita, The ProjectLa Esperanza, El Calvario, La Danta, El Limonar, Los Primos, Los Salsales, La Florida, No Hay Como Dios, Villa Marín and Tierra Nueva.

Similarly, in the Casacara circuit, new structures will be installed, armed with medium voltage and branches that interfere with the electrical networks will be removed, activities that demand the service interruption from 7:10 a.m. to 5:45 p.m.on Calle 10 with Carrera 2 in the Casacara district.

-The Copey: of 6:00 a.m. a 4:00 p.m.a distribution transformer will be renewed, for this, the electrical fluid will be suspended in Carrera 3 and Calle 5 of the Caracolicito district.

You may also like

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More

Privacy & Cookies Policy